Strathy Wood Wind Farm

Developer as published, connection site, reference: RWE Renewables UK Onshore Wind Limited. Strathy Wood 132/33kV Substation (SHET). PRO-000154.

Sign in to watch this project
Capacity63.5 MWOnshore wind, Gate 2
Connection date31 Dec 2029Status as printed: Consents Approved
First date seen 1 May 2025, difference +1705 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

202520272029File dated 2026-09-11: connection date 2025-05-01May 2025File dated 2026-10-20: connection date 2029-12-31Dec 202911 Sep202620 Oct2026
202520272029File dated 2026-09-11: connection date 2025-05-01May 2025File dated 2026-10-20: connection date 2029-12-31Dec 202911 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Not printed in this file; printed in the previous one. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedpresent → missingReceipt: NESO TEC Register, file dated 20 Oct 2026Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1917
  2. 20 Oct 2026. Not printed in this file; printed in the previous one. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedpresent → missingReceipt: NESO TEC Register, file dated 20 Oct 2026Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1916
  3. 20 Oct 2026. Project name printed as Strathy Wood Wind Farm (previous file: Strathy Wood). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedStrathy Wood → Strathy Wood Wind FarmReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581
  4. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Awaiting Consents). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedAwaiting Consents → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581
  5. 20 Oct 2026. Stage printed as blank (previous file: 1). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was imported1 → blankReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581
  6. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581
  7. 20 Oct 2026. MW Effective From printed as 31 Dec 2029 (previous file: 1 May 2025), 1,705 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1705 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581
  8. 20 Oct 2026. Export capacity printed as 63.5 MW (previous file: 54.4 MW), +9.1 MW. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was imported54.4 → 63.5Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581
  9. 20 Oct 2026. Printed again after being absent from the previous file. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedleft_register → presentReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1943Receipt: NESO TEC Register, file dated 31 May 2024, row 1581

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.