2,187.3 MWTotal MW as printed
2 / 1Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Built: 0.2 GW (9%)
  • Queued: 2.0 GW (91%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.2
Queued2.0
MW by technology
TechnologyProjectsMW
Hybrid71,362.4 MW
Onshore wind14824.9 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Tween Bridge Solar ParkHybrid800 MW30 Oct 2037ScopingTrent Valley North Connection Node B 400kV Substation
Deucheran Hill 2 Wind FarmHybrid165 MW31 Oct 2034ScopingDEUCHERAN HILL 2 132KV SUBSTATION
Balinoe Wind FarmHybrid160.6 MW31 Oct 2034ScopingBalinoe 132kV substation
Eredine Wind FarmHybrid105 MW1 Nov 2029ScopingAn Suidhe 275/33kV
Daer Wind Farm (RWE Renewables UK Onshore Wind Limited)Onshore wind96 MW1 Aug 2028Awaiting ConsentsDaer Wind Farm 132/33kV
Ceislein Wind FarmOnshore wind85.8 MW31 Oct 2030ScopingCeislien Wind Farm
Creachan Wind Farm (RWE Renewables UK Onshore Wind Limited)Onshore wind79.2 MW31 Oct 2030ScopingCreachan Wind Farm 132/33kV Substation
Grimshader Wind FarmOnshore wind79.2 MW31 Oct 2033ScopingGrimshader Wind Farm Substation132 KV
Lorg Wind Farm (RWE Renewables UK Onshore Wind Limited)Onshore wind69.5 MW7 Apr 2028Awaiting ConsentsLorg Wind Farm 132/32kV
Enoch Hill (RWE Renewables UK Onshore Wind Limited)Hybrid69 MWnot statedBuiltEnoch Hill 132/33kV Substation
Gaerwen Wind FarmOnshore wind67 MW1 Jun 2027Awaiting ConsentsGwyddelwern 400kV Substation
Heastabhal Wind Farm (RWE Renewables UK Onshore Wind Limited)Onshore wind66 MW31 Oct 2033ScopingHeastabhal Wind Farm Substation 132 KV
Strathy Wood Wind FarmOnshore wind63.5 MW31 Dec 2029Consents ApprovedStrathy Wood 132/33kV Substation
Golticlay Wind FarmOnshore wind58 MW31 Jul 2026ScopingMybster 1 132/33kV Substation
Clachaig Glen Wind FarmHybrid52.8 MW31 Oct 2034Consents ApprovedCarradale 2 132/33kV GSP Substation
Camster Wind FarmOnshore wind50 MWnot statedBuiltMybster 132/33kV Substation
Camster 2 Wind FarmOnshore wind38 MWnot statedBuiltMybster 132/33kV Substation
Lorg Extension Wind Farm (RWE Renewables UK Onshore Wind Limited)Onshore wind33 MW13 Aug 2029ScopingLorg Extension Wind Farm 132/33kV Substation
RosehallOnshore wind24.7 MWnot statedBuiltShin 1 GSP
Deucheran Hill (RWE Renewables UK Onshore Wind Limited)Onshore wind15 MWnot statedBuiltDeucheran Hill GSP
Enoch Hill 2 Wind Farm (RWE Renewables UK Onshore Wind Limited)Hybrid10 MW30 Apr 2027Awaiting ConsentsEnoch Hill 2 Wind Farm 33kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.