Carradale 2 132/33kV GSP Substation

NESO connection site, host SHET.

Contracted here0.13 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Apr 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue132.8 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Clachaig Glen Wind Farm7 Nov 202530 Apr 202547.6 MW
West Torrisdale31 May 202431 May 202850 MW
Clachaig Glen Wind Farm7 Nov 202531 Oct 20345.2 MW
Glencreggan Wind Farm7 Nov 202531 Oct 203430 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2025: 48 MW2028: 98 MW2034: 133 MW202520272029203120332034133 MW
0 MW100 MW200 MW2025: 48 MW2028: 98 MW2034: 133 MW2025202820312034133 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202547.6 MW
202897.6 MW
2034132.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Clachaig Glen Wind Farm47.6 MW0 MW30 Apr 20252gate 2Awaiting Consents
2West Torrisdale50 MW47.6 MW31 May 2028not statedgate not printedScoping
3Clachaig Glen Wind Farm5.2 MW97.6 MW31 Oct 2034not statedgate not printedConsents Approved
4Glencreggan Wind Farm30 MW102.8 MW31 Oct 2034not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025147.6 MW
2028150 MW
2034235.2 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Clachaig Glen Wind FarmHybrid52.8 MW31 Oct 2034Consents Approved
West TorrisdaleOnshore wind50 MW31 May 2028Scoping
Glencreggan Wind FarmOnshore wind30 MW31 Oct 2034Scoping