Capacity50 MWOnshore wind
Connection date31 May 2028Status as printed: Scoping
First date seen 30 Apr 2027, difference +397 dayscalculated by N84
First date seen 30 Apr 2027, difference +397 dayscalculated by N84
MW ahead in N84's order at this site47.6 MWcalculated by N84
Connection date, edition by edition
The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Connection site printed as Carradale 2 132/33kV GSP Substation (previous file: Carradale 1 GSP). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedCarradale 1 GSP → Carradale 2 132/33kV GSP SubstationReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2133Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2104
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.