Penwortham BESS

Developer as published, connection site, reference: CSE28 LIMITED. Penwortham 400kV Substation (NGET). PRO-002037.

Sign in to watch this project
Capacity57 MWBattery storage, Gate 1
Connection date1 Jun 2031Status as printed: Scoping
First date seen 1 Jun 2027, difference +1461 dayscalculated by N84
MW ahead in N84's order at this site2,037 MWcalculated by N84

Connection date, edition by edition

20312032File dated 2024-05-31: connection date 2031-06-01Jun 2031File dated 2026-10-20: connection date 2031-06-0131 May202420 Oct2026
20312032File dated 2024-05-31: connection date 2031-06-01Jun 2031File dated 2026-10-20: connection date 2031-06-0131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.