The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Penwortham BESS
31 May 2024 to 30 Oct 2028 (gate 2) - Morecambe Offshore Wind Farm
31 May 2024 to 30 Jun 2029 (gate not printed) - Morgan Offshore Wind Farm
31 May 2024 to 30 Nov 2029 (gate not printed) - Penwortham BESS
31 May 2024 to 1 Jun 2031 (gate 1) - Penwortham Green Energy Centre
31 May 2024 to 30 Oct 2035 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Penwortham BESS | 31 May 2024 | 30 Oct 2028 | 57 MW |
| Morecambe Offshore Wind Farm | 31 May 2024 | 30 Jun 2029 | 480 MW |
| Morgan Offshore Wind Farm | 31 May 2024 | 30 Nov 2029 | 1,500 MW |
| Penwortham BESS | 31 May 2024 | 1 Jun 2031 | 57 MW |
| Penwortham Green Energy Centre | 31 May 2024 | 30 Oct 2035 | 600 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2028 | 57 MW |
| 2029 | 2,037 MW |
| 2031 | 2,094 MW |
| 2035 | 2,694 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Penwortham BESS | 57 MW | 0 MW | 30 Oct 2028 | 2 | gate 2 | Consents Approved |
| 2 | Morecambe Offshore Wind Farm | 480 MW | 57 MW | 30 Jun 2029 | not stated | gate not printed | Scoping |
| 3 | Morgan Offshore Wind Farm | 1,500 MW | 537 MW | 30 Nov 2029 | not stated | gate not printed | Scoping |
| 4 | Penwortham BESS | 57 MW | 2,037 MW | 1 Jun 2031 | 1 | gate 1 | Scoping |
| 5 | Penwortham Green Energy Centre | 600 MW | 2,094 MW | 30 Oct 2035 | 1 | gate 1 | Awaiting Consents |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2028 | 1 | 57 MW |
| 2029 | 2 | 1,980 MW |
| 2031 | 1 | 57 MW |
| 2035 | 1 | 600 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Morgan Offshore Wind Farm | Offshore wind | 1,500 MW | 30 Nov 2029 | Scoping |
| Penwortham Green Energy Centre | Hybrid | 600 MW | 30 Oct 2035 | Awaiting Consents |
| Morecambe Offshore Wind Farm | Offshore wind | 480 MW | 30 Jun 2029 | Scoping |
| Penwortham BESS | Battery storage | 57 MW | 1 Jun 2031 | Scoping |
| Penwortham BESS | Battery storage | 57 MW | 30 Oct 2028 | Consents Approved |
| Penwortham (Redscar) | Battery storage | 40 MW | not stated | Built |
| Bispham BEGA | Gas | 20 MW | not stated | Built |