N84 Grid

Penwortham 400kV Substation

NESO connection site, host NGET.

Contracted here2.69 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date30 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,694 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Penwortham BESS31 May 202430 Oct 202857 MW
Morecambe Offshore Wind Farm31 May 202430 Jun 2029480 MW
Morgan Offshore Wind Farm31 May 202430 Nov 20291,500 MW
Penwortham BESS31 May 20241 Jun 203157 MW
Penwortham Green Energy Centre31 May 202430 Oct 2035600 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2028: 57 MW2029: 2.0 GW2031: 2.1 GW2035: 2.7 GW202820292030203120322033203420352.7 GW
0 MW2.0 GW4.0 GW2028: 57 MW2029: 2.0 GW2031: 2.1 GW2035: 2.7 GW20282030203220352.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202857 MW
20292,037 MW
20312,094 MW
20352,694 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Penwortham BESS57 MW0 MW30 Oct 20282gate 2Consents Approved
2Morecambe Offshore Wind Farm480 MW57 MW30 Jun 2029not statedgate not printedScoping
3Morgan Offshore Wind Farm1,500 MW537 MW30 Nov 2029not statedgate not printedScoping
4Penwortham BESS57 MW2,037 MW1 Jun 20311gate 1Scoping
5Penwortham Green Energy Centre600 MW2,094 MW30 Oct 20351gate 1Awaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028157 MW
202921,980 MW
2031157 MW
20351600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Morgan Offshore Wind FarmOffshore wind1,500 MW30 Nov 2029Scoping
Penwortham Green Energy CentreHybrid600 MW30 Oct 2035Awaiting Consents
Morecambe Offshore Wind FarmOffshore wind480 MW30 Jun 2029Scoping
Penwortham BESSBattery storage57 MW1 Jun 2031Scoping
Penwortham BESSBattery storage57 MW30 Oct 2028Consents Approved
Penwortham (Redscar)Battery storage40 MWnot statedBuilt
Bispham BEGAGas20 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.