N84 Grid

WindyHill BESS2 Facility

Developer as published, connection site, reference: Windyhill Grid 2 Ltd. Windyhill 275/132kV (SPT). PRO-002032.

Sign in to watch this project
Capacity200 MWBattery storage
Connection date27 Jul 2025Status as printed: Scoping
First date seen 30 Sep 2024, difference +300 dayscalculated by N84
MW ahead in N84's order at this site200 MWcalculated by N84

Connection date, edition by edition

20252026File dated 2024-05-31: connection date 2025-07-27Jul 2025File dated 2026-10-20: connection date 2025-07-2731 May202420 Oct2026
20252026File dated 2024-05-31: connection date 2025-07-27Jul 2025File dated 2026-10-20: connection date 2025-07-2731 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.