N84 Grid

Windyhill 275/132kV

NESO connection site, host SPT.

Contracted here0.40 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date27 Jul 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue400 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
WindyHill Energy Storage Facility31 May 202431 Dec 2027200 MW
WindyHill BESS2 Facility31 May 202427 Jul 2025200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2025: 200 MW2027: 400 MW202520262027400 MW
0 MW200 MW400 MW2025: 200 MW2027: 400 MW202520262027400 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2025200 MW
2027400 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1WindyHill Energy Storage Facility200 MW0 MW31 Dec 20272gate 2Consents Approved
2WindyHill BESS2 Facility200 MW200 MW27 Jul 2025not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20251200 MW
20271200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
WindyHill BESS2 FacilityBattery storage200 MW27 Jul 2025Scoping
WindyHill Energy Storage FacilityBattery storage200 MW31 Dec 2027Consents Approved

Supported by National Energy SO Open Data