The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- WindyHill Energy Storage Facility
31 May 2024 to 31 Dec 2027 (gate 2) - WindyHill BESS2 Facility
31 May 2024 to 27 Jul 2025, date already passed (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| WindyHill Energy Storage Facility | 31 May 2024 | 31 Dec 2027 | 200 MW |
| WindyHill BESS2 Facility | 31 May 2024 | 27 Jul 2025 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 200 MW |
| 2027 | 400 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | WindyHill Energy Storage Facility | 200 MW | 0 MW | 31 Dec 2027 | 2 | gate 2 | Consents Approved |
| 2 | WindyHill BESS2 Facility | 200 MW | 200 MW | 27 Jul 2025 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 200 MW |
| 2027 | 1 | 200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| WindyHill BESS2 Facility | Battery storage | 200 MW | 27 Jul 2025 | Scoping |
| WindyHill Energy Storage Facility | Battery storage | 200 MW | 31 Dec 2027 | Consents Approved |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.