Zenobe Spennymoor BESS

Developer as published, connection site, reference: ZENOBE ENERGY LIMITED. Wearside Connection Node D 400kV Substation (NGET). PRO-003692.

Sign in to watch this project
Capacity300 MWBattery storage, Gate 1
Connection date30 Oct 2035Status as printed: Scoping
MW ahead in N84's order at this site400 MWcalculated by N84

Connection date, edition by edition

203420352036File dated 2026-09-11: connection date 2034-10-30Oct 2034File dated 2026-10-20: connection date 2035-10-30Oct 203511 Sep202620 Oct2026
203420352036File dated 2026-09-11: connection date 2034-10-30Oct 2034File dated 2026-10-20: connection date 2035-10-30Oct 203511 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 30 Oct 2035 (previous file: 30 Oct 2034), 365 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +365 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2226Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2197

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.