Wearside Connection Node D 400kV Substation

NESO connection site, host NGET.

Contracted here1.30 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Oct 2035Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,300 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Spennymoor BESS Station31 May 202430 Oct 2035400 MW
Zenobe Spennymoor BESS27 Sep 202430 Oct 2035300 MW
Redhall BESS20 Dec 202430 Oct 2035300 MW
Overton Grange BESS22 Jul 202530 Oct 2035300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2035: 1.3 GW20351.3 GW
0 MW1.0 GW2.0 GW2035: 1.3 GW20351.3 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20351,300 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Spennymoor BESS Station400 MW0 MW30 Oct 20351gate 1Scoping
2Zenobe Spennymoor BESS300 MW400 MW30 Oct 20351gate 1Scoping
3Redhall BESS300 MW700 MW30 Oct 20351gate 1Scoping
4Overton Grange BESS300 MW1,000 MW30 Oct 20351gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203541,300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Spennymoor BESS StationBattery storage400 MW30 Oct 2035Scoping
Zenobe Spennymoor BESSBattery storage300 MW30 Oct 2035Scoping
Overton Grange BESSBattery storage300 MW30 Oct 2035Scoping
Redhall BESSBattery storage300 MW30 Oct 2035Scoping