Capacity57 MWHybrid, Gate 2
Connection date30 May 2027Status as printed: Consents Approved
First date seen 30 Jun 2025, difference +699 dayscalculated by N84
First date seen 30 Jun 2025, difference +699 dayscalculated by N84
MW ahead in N84's order at this site50 MWcalculated by N84
Connection date, edition by edition
Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Project Status printed as Consents Approved (previous file: Awaiting Consents). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedAwaiting Consents → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2201Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2173
- 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 2201Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2173
- 20 Oct 2026. MW Effective From printed as 30 May 2027 (previous file: 31 Oct 2025), 576 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +576 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2201Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2173
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.