N84 Grid

Huntingdon High Impact Energy Hub 1

Developer as published, connection site, reference: TELIS ENERGY UK LIMITED. West Anglia Connection Node H 400kVSubstation (NGET). PRO-004507.

Sign in to watch this project
Capacity1,000 MWHybrid, Gate 1
Connection date31 Oct 2034Status as printed: Awaiting Consents
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20342035File dated 2024-12-20: connection date 2034-10-31Oct 2034File dated 2026-10-20: connection date 2034-10-3120 Dec202420 Oct2026
20342035File dated 2024-12-20: connection date 2034-10-31Oct 2034File dated 2026-10-20: connection date 2034-10-3120 Dec202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 20 Dec 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data