The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Huntingdon High Impact Energy Hub 1
20 Dec 2024 to 31 Oct 2034 (gate 1) - Huntingdon High Impact Energy Hub 2
22 Jul 2025 to 31 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Huntingdon High Impact Energy Hub 1 | 20 Dec 2024 | 31 Oct 2034 | 1,000 MW |
| Huntingdon High Impact Energy Hub 2 | 22 Jul 2025 | 31 Oct 2034 | 1,000 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2034 | 2,000 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Huntingdon High Impact Energy Hub 1 | 1,000 MW | 0 MW | 31 Oct 2034 | 1 | gate 1 | Awaiting Consents |
| 2 | Huntingdon High Impact Energy Hub 2 | 1,000 MW | 1,000 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2034 | 2 | 2,000 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Huntingdon High Impact Energy Hub 2 | Hybrid | 1,000 MW | 31 Oct 2034 | Scoping |
| Huntingdon High Impact Energy Hub 1 | Hybrid | 1,000 MW | 31 Oct 2034 | Awaiting Consents |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.