Ewerby

Developer as published, connection site, reference: Leoda Solar Farm Limited. Navenby 400kV Substation (NGET). PRO-002017.

Sign in to watch this project
Capacity500 MWHybrid, Gate 1
Connection date30 Oct 2035Status as printed: Scoping
First date seen 30 Oct 2029, difference +2191 dayscalculated by N84
MW ahead in N84's order at this site4,238.9 MWcalculated by N84

Connection date, edition by edition

2029203120332035File dated 2026-09-11: connection date 2029-10-30Oct 2029File dated 2026-10-20: connection date 2035-10-30Oct 203511 Sep202620 Oct2026
2029203120332035File dated 2026-09-11: connection date 2029-10-30Oct 2029File dated 2026-10-20: connection date 2035-10-30Oct 203511 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 30 Oct 2035 (previous file: 30 Oct 2029), 2,191 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +2191 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 756Receipt: NESO TEC Register, file dated 11 Sep 2026, row 735

Supported by National Energy SO Open Data