Navenby 400kV Substation

NESO connection site, host NGET.

Contracted here4.90 GWNot yet connected, as printed
Entries in the queue12entries with a printed MW
Earliest connection date30 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,820 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Springwell31 May 202430 Oct 2029400 MW
Springwell31 May 202430 Oct 2030400 MW
Housham PV & BESS31 May 202430 May 2033240 MW
Springwell31 May 20241 Jun 2033800 MW
Navenby GEC (Ethos Green)31 May 202430 Oct 2033580 MW
Bicker Drove31 May 202430 May 2034400 MW
Bicker Fen BESS31 May 202430 Oct 2034249.9 MW
Cliff Hill Energy Farm31 May 202430 Oct 2034800 MW
Denton Estate Solar PV and BESS31 May 202430 Oct 2034129 MW
Forepower Lincoln (250) Ltd22 Jul 202530 Oct 2034240 MW
Ewerby31 May 202430 Oct 2035500 MW
Vicarage Drove BESS Limited22 Jul 202530 Oct 2039160 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2029: 400 MW2030: 800 MW2033: 2.4 GW2034: 4.2 GW2035: 4.7 GW2039: 4.9 GW2029203120332035203720394.9 GW
0 MW2.5 GW5.0 GW2029: 400 MW2030: 800 MW2033: 2.4 GW2034: 4.2 GW2035: 4.7 GW2039: 4.9 GW20292032203520394.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029400 MW
2030800 MW
20332,420 MW
20344,238.9 MW
20354,738.9 MW
20394,898.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Springwell400 MW0 MW30 Oct 2029not statedgate not printedScoping
2Springwell400 MW400 MW30 Oct 2030not statedgate not printedScoping
3Housham PV & BESS240 MW800 MW30 May 2033not statedgate not printedScoping
4Springwell800 MW1,040 MW1 Jun 2033not statedgate not printedScoping
5Navenby GEC (Ethos Green)580 MW1,840 MW30 Oct 20331gate 1Awaiting Consents
6Bicker Drove400 MW2,420 MW30 May 20341gate 1Scoping
7Bicker Fen BESS249.9 MW2,820 MW30 Oct 2034not statedgate not printedScoping
8Cliff Hill Energy Farm800 MW3,069.9 MW30 Oct 20341gate 1Scoping
9Denton Estate Solar PV and BESS129 MW3,869.9 MW30 Oct 20341gate 1Scoping
10Forepower Lincoln (250) Ltd240 MW3,998.9 MW30 Oct 20341gate 1Scoping
11Ewerby500 MW4,238.9 MW30 Oct 20351gate 1Scoping
12Vicarage Drove BESS Limited160 MW4,738.9 MW30 Oct 2039not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291400 MW
20301400 MW
203331,620 MW
203451,818.9 MW
20351500 MW
20391160 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
SpringwellHybrid1,600 MW1 Jun 2033Scoping
Cliff Hill Energy FarmHybrid800 MW30 Oct 2034Scoping
Navenby GEC (Ethos Green)Hybrid580 MW30 Oct 2033Awaiting Consents
EwerbyHybrid500 MW30 Oct 2035Scoping
Bicker DroveBattery storage400 MW30 May 2034Scoping
Bicker Fen BESSHybrid249.9 MW30 Oct 2034Scoping
Forepower Lincoln (250) LtdBattery storage240 MW30 Oct 2034Scoping
Housham PV & BESSHybrid240 MW30 May 2033Scoping
Vicarage Drove BESS LimitedBattery storage160 MW30 Oct 2039Scoping
Denton Estate Solar PV and BESSHybrid129 MW30 Oct 2034Scoping