The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Springwell
31 May 2024 to 30 Oct 2029 (gate not printed) - Springwell
31 May 2024 to 30 Oct 2030 (gate not printed) - Housham PV & BESS
31 May 2024 to 30 May 2033 (gate not printed) - Springwell
31 May 2024 to 1 Jun 2033 (gate not printed) - Navenby GEC (Ethos Green)
31 May 2024 to 30 Oct 2033 (gate 1) - Bicker Drove
31 May 2024 to 30 May 2034 (gate 1) - Bicker Fen BESS
31 May 2024 to 30 Oct 2034 (gate not printed) - Cliff Hill Energy Farm
31 May 2024 to 30 Oct 2034 (gate 1) - Denton Estate Solar PV and BESS
31 May 2024 to 30 Oct 2034 (gate 1) - Forepower Lincoln (250) Ltd
22 Jul 2025 to 30 Oct 2034 (gate 1) - Ewerby
31 May 2024 to 30 Oct 2035 (gate 1) - Vicarage Drove BESS Limited
22 Jul 2025 to 30 Oct 2039 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Springwell | 31 May 2024 | 30 Oct 2029 | 400 MW |
| Springwell | 31 May 2024 | 30 Oct 2030 | 400 MW |
| Housham PV & BESS | 31 May 2024 | 30 May 2033 | 240 MW |
| Springwell | 31 May 2024 | 1 Jun 2033 | 800 MW |
| Navenby GEC (Ethos Green) | 31 May 2024 | 30 Oct 2033 | 580 MW |
| Bicker Drove | 31 May 2024 | 30 May 2034 | 400 MW |
| Bicker Fen BESS | 31 May 2024 | 30 Oct 2034 | 249.9 MW |
| Cliff Hill Energy Farm | 31 May 2024 | 30 Oct 2034 | 800 MW |
| Denton Estate Solar PV and BESS | 31 May 2024 | 30 Oct 2034 | 129 MW |
| Forepower Lincoln (250) Ltd | 22 Jul 2025 | 30 Oct 2034 | 240 MW |
| Ewerby | 31 May 2024 | 30 Oct 2035 | 500 MW |
| Vicarage Drove BESS Limited | 22 Jul 2025 | 30 Oct 2039 | 160 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2029 | 400 MW |
| 2030 | 800 MW |
| 2033 | 2,420 MW |
| 2034 | 4,238.9 MW |
| 2035 | 4,738.9 MW |
| 2039 | 4,898.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Springwell | 400 MW | 0 MW | 30 Oct 2029 | not stated | gate not printed | Scoping |
| 2 | Springwell | 400 MW | 400 MW | 30 Oct 2030 | not stated | gate not printed | Scoping |
| 3 | Housham PV & BESS | 240 MW | 800 MW | 30 May 2033 | not stated | gate not printed | Scoping |
| 4 | Springwell | 800 MW | 1,040 MW | 1 Jun 2033 | not stated | gate not printed | Scoping |
| 5 | Navenby GEC (Ethos Green) | 580 MW | 1,840 MW | 30 Oct 2033 | 1 | gate 1 | Awaiting Consents |
| 6 | Bicker Drove | 400 MW | 2,420 MW | 30 May 2034 | 1 | gate 1 | Scoping |
| 7 | Bicker Fen BESS | 249.9 MW | 2,820 MW | 30 Oct 2034 | not stated | gate not printed | Scoping |
| 8 | Cliff Hill Energy Farm | 800 MW | 3,069.9 MW | 30 Oct 2034 | 1 | gate 1 | Scoping |
| 9 | Denton Estate Solar PV and BESS | 129 MW | 3,869.9 MW | 30 Oct 2034 | 1 | gate 1 | Scoping |
| 10 | Forepower Lincoln (250) Ltd | 240 MW | 3,998.9 MW | 30 Oct 2034 | 1 | gate 1 | Scoping |
| 11 | Ewerby | 500 MW | 4,238.9 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 12 | Vicarage Drove BESS Limited | 160 MW | 4,738.9 MW | 30 Oct 2039 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2029 | 1 | 400 MW |
| 2030 | 1 | 400 MW |
| 2033 | 3 | 1,620 MW |
| 2034 | 5 | 1,818.9 MW |
| 2035 | 1 | 500 MW |
| 2039 | 1 | 160 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Springwell | Hybrid | 1,600 MW | 1 Jun 2033 | Scoping |
| Cliff Hill Energy Farm | Hybrid | 800 MW | 30 Oct 2034 | Scoping |
| Navenby GEC (Ethos Green) | Hybrid | 580 MW | 30 Oct 2033 | Awaiting Consents |
| Ewerby | Hybrid | 500 MW | 30 Oct 2035 | Scoping |
| Bicker Drove | Battery storage | 400 MW | 30 May 2034 | Scoping |
| Bicker Fen BESS | Hybrid | 249.9 MW | 30 Oct 2034 | Scoping |
| Forepower Lincoln (250) Ltd | Battery storage | 240 MW | 30 Oct 2034 | Scoping |
| Housham PV & BESS | Hybrid | 240 MW | 30 May 2033 | Scoping |
| Vicarage Drove BESS Limited | Battery storage | 160 MW | 30 Oct 2039 | Scoping |
| Denton Estate Solar PV and BESS | Hybrid | 129 MW | 30 Oct 2034 | Scoping |
Supported by National Energy SO Open Data