New Deer BESS Station

Developer as published, connection site, reference: ABBOTSHAUGH ENERGY STORAGE LIMITED. New Deer 2 400kV Substation (SHET). PRO-001856.

Sign in to watch this project
Capacity500 MWBattery storage, Gate 1
Connection date31 Oct 2033Status as printed: Scoping
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

203220332034File dated 2026-09-11: connection date 2032-07-30Jul 2032File dated 2026-10-20: connection date 2033-10-31Oct 203311 Sep202620 Oct2026
203220332034File dated 2026-09-11: connection date 2032-07-30Jul 2032File dated 2026-10-20: connection date 2033-10-31Oct 203311 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2033 (previous file: 30 Jul 2032), 458 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +458 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1535Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1515

Supported by National Energy SO Open Data