N84 Grid

New Deer 2 400kV Substation

NESO connection site, host SHET.

Contracted here2.06 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,055 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
New Deer BESS Station31 May 202431 Oct 2033500 MW
New Deer Battery Storage31 May 202431 Oct 2033500 MW
Peterhead PV and BESS Station31 May 202431 Oct 2033480 MW
L48 BESS Burnside31 May 202431 Oct 2033200 MW
UPPER GREENFIELDS BESS31 May 202431 Oct 2033175 MW
New Deer 2 BESS20 Dec 202431 Oct 2033200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2033: 2.1 GW20332.1 GW
0 MW1.3 GW2.5 GW2033: 2.1 GW20332.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20332,055 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1New Deer BESS Station500 MW0 MW31 Oct 20331gate 1Scoping
2New Deer Battery Storage500 MW500 MW31 Oct 20331gate 1Scoping
3Peterhead PV and BESS Station480 MW1,000 MW31 Oct 2033not statedgate not printedAwaiting Consents
4L48 BESS Burnside200 MW1,480 MW31 Oct 20331gate 1Scoping
5UPPER GREENFIELDS BESS175 MW1,680 MW31 Oct 20331gate 1Scoping
6New Deer 2 BESS200 MW1,855 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203362,055 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
New Deer BESS StationBattery storage500 MW31 Oct 2033Scoping
New Deer Battery StorageBattery storage500 MW31 Oct 2033Scoping
Peterhead PV and BESS StationHybrid480 MW31 Oct 2033Awaiting Consents
New Deer 2 BESSBattery storage200 MW31 Oct 2033Scoping
L48 BESS BurnsideBattery storage200 MW31 Oct 2033Scoping
UPPER GREENFIELDS BESSBattery storage175 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.