Montreathmont Moor Forest

Developer as published, connection site, reference: Montreathmont Energy Centre Limited. Lunanhead GSP (SHET). PRO-001849.

Sign in to watch this project
Capacity34.38 MWHybrid, Gate 2
Connection date31 Oct 2026Status as printed: Consents Approved
First date seen 31 Oct 2025, difference +365 dayscalculated by N84
MW ahead in N84's order at this site71.7 MWcalculated by N84

Connection date, edition by edition

20262027202820292030File dated 2026-09-11: connection date 2029-10-08Oct 2029File dated 2026-10-20: connection date 2026-10-31Oct 202611 Sep202620 Oct2026
20262027202820292030File dated 2026-09-11: connection date 2029-10-08Oct 2029File dated 2026-10-20: connection date 2026-10-31Oct 202611 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1452Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1432
  2. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1452Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1432
  3. 20 Oct 2026. MW Effective From printed as 31 Oct 2026 (previous file: 8 Oct 2029), 1,073 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -1073 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1452Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1432

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.