N84 Grid

Lunanhead GSP

NESO connection site, host SHET.

Contracted here0.26 GWNot yet connected, as printed
Entries in the queue14entries with a printed MW
Earliest connection date30 Nov 2021Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue138.08 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lunanhead Battery7 Nov 202530 Sep 202649.9 MW
Lunanhead Solar Park7 Nov 202531 Oct 202621.8 MW
Montreathmont Moor Forest31 May 202431 Oct 202634.38 MW
Lunanhead GSP7 Nov 202526 Oct 20275 MW
North Mains Battery Storage Park7 Nov 202531 Oct 202722 MW
Carsebank PV7 Nov 202530 Nov 20215 MW
Howmuir PV7 Nov 202530 Nov 20215 MW
Orchardbank Battery Storage7 Nov 202520 Apr 20249.99 MW
Forfar Solar - DNO7 Nov 202531 Oct 202527.8 MW
Tailors Wynd7 Nov 202531 Oct 20250.97 MW
Exhibit U Marywell Works7 Nov 202531 Oct 20250.19 MW
Forfar WWTW7 Nov 202531 Oct 20250.2 MW
Fofar Solar Farm7 Nov 202531 Oct 202629.8 MW
Cossans Solar/BESS Project7 Nov 202531 Oct 203249.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2021: 10 MW2024: 20 MW2025: 49 MW2026: 185 MW2027: 212 MW2032: 262 MW202120232025202720292032262 MW
0 MW200 MW400 MW2021: 10 MW2024: 20 MW2025: 49 MW2026: 185 MW2027: 212 MW2032: 262 MW20212024202720302032262 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202110 MW
202419.99 MW
202549.15 MW
2026185.03 MW
2027212.03 MW
2032261.93 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lunanhead Battery49.9 MW0 MW30 Sep 20262gate 2Consents Approved
2Lunanhead Solar Park21.8 MW49.9 MW31 Oct 20262gate 2Consents Approved
3Montreathmont Moor Forest34.38 MW71.7 MW31 Oct 20262gate 2Consents Approved
4Lunanhead GSP5 MW106.08 MW26 Oct 20272gate 2Consents Approved
5North Mains Battery Storage Park22 MW111.08 MW31 Oct 20272gate 2Consents Approved
6Carsebank PV5 MW133.08 MW30 Nov 2021not statedgate not printedConsents Approved
7Howmuir PV5 MW138.08 MW30 Nov 2021not statedgate not printedConsents Approved
8Orchardbank Battery Storage9.99 MW143.08 MW20 Apr 2024not statedgate not printedConsents Approved
9Forfar Solar - DNO27.8 MW153.07 MW31 Oct 2025not statedgate not printedScoping
10Tailors Wynd0.97 MW180.87 MW31 Oct 2025not statedgate not printedScoping
11Exhibit U Marywell Works0.19 MW181.84 MW31 Oct 2025not statedgate not printedScoping
12Forfar WWTW0.2 MW182.03 MW31 Oct 2025not statedgate not printedConsents Approved
13Fofar Solar Farm29.8 MW182.23 MW31 Oct 20261gate 1Scoping
14Cossans Solar/BESS Project49.9 MW212.03 MW31 Oct 2032not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2021210 MW
202419.99 MW
2025429.16 MW
20264135.88 MW
2027227 MW
2032149.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Cossans Solar/BESS ProjectHybrid49.9 MW31 Oct 2032Scoping
Lunanhead BatteryBattery storage49.9 MW30 Sep 2026Consents Approved
Montreathmont Moor ForestHybrid34.38 MW31 Oct 2026Consents Approved
Fofar Solar FarmSolar29.8 MW31 Oct 2026Scoping
Forfar Solar - DNOSolar27.8 MW31 Oct 2025Scoping
North Mains Battery Storage ParkBattery storage22 MW31 Oct 2027Consents Approved
Lunanhead Solar ParkSolar21.8 MW31 Oct 2026Consents Approved
Orchardbank Battery StorageBattery storage9.99 MW20 Apr 2024Consents Approved
Dragonhall Farm PVSolar5 MWnot statedBuilt
Pressock Farm PVSolar5 MWnot statedBuilt
Howmuir PVSolar5 MW30 Nov 2021Consents Approved
Lunanhead GSP (Scottish Hydro Electric Power Distribution Plc)Battery storage5 MW26 Oct 2027Consents Approved
Carsebank PVSolar5 MW30 Nov 2021Consents Approved
Pitscandly Farm PVSolar4.13 MWnot statedBuilt
Tailors WyndSolar0.97 MW31 Oct 2025Scoping
Forfar WWTWSolar0.2 MW31 Oct 2025Consents Approved
Exhibit U Marywell WorksGas0.19 MW31 Oct 2025Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.