The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Lunanhead Battery
7 Nov 2025 to 30 Sep 2026, date already passed (gate 2) - Lunanhead Solar Park
7 Nov 2025 to 31 Oct 2026 (gate 2) - Montreathmont Moor Forest
31 May 2024 to 31 Oct 2026 (gate 2) - Lunanhead GSP
7 Nov 2025 to 26 Oct 2027 (gate 2) - North Mains Battery Storage Park
7 Nov 2025 to 31 Oct 2027 (gate 2) - Carsebank PV
7 Nov 2025 to 30 Nov 2021, date already passed (gate not printed) - Howmuir PV
7 Nov 2025 to 30 Nov 2021, date already passed (gate not printed) - Orchardbank Battery Storage
7 Nov 2025 to 20 Apr 2024, date already passed (gate not printed) - Forfar Solar - DNO
7 Nov 2025 to 31 Oct 2025, date already passed (gate not printed) - Tailors Wynd
7 Nov 2025 to 31 Oct 2025, date already passed (gate not printed) - Exhibit U Marywell Works
7 Nov 2025 to 31 Oct 2025, date already passed (gate not printed) - Forfar WWTW
7 Nov 2025 to 31 Oct 2025, date already passed (gate not printed) - Fofar Solar Farm
7 Nov 2025 to 31 Oct 2026 (gate 1) - Cossans Solar/BESS Project
7 Nov 2025 to 31 Oct 2032 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Lunanhead Battery | 7 Nov 2025 | 30 Sep 2026 | 49.9 MW |
| Lunanhead Solar Park | 7 Nov 2025 | 31 Oct 2026 | 21.8 MW |
| Montreathmont Moor Forest | 31 May 2024 | 31 Oct 2026 | 34.38 MW |
| Lunanhead GSP | 7 Nov 2025 | 26 Oct 2027 | 5 MW |
| North Mains Battery Storage Park | 7 Nov 2025 | 31 Oct 2027 | 22 MW |
| Carsebank PV | 7 Nov 2025 | 30 Nov 2021 | 5 MW |
| Howmuir PV | 7 Nov 2025 | 30 Nov 2021 | 5 MW |
| Orchardbank Battery Storage | 7 Nov 2025 | 20 Apr 2024 | 9.99 MW |
| Forfar Solar - DNO | 7 Nov 2025 | 31 Oct 2025 | 27.8 MW |
| Tailors Wynd | 7 Nov 2025 | 31 Oct 2025 | 0.97 MW |
| Exhibit U Marywell Works | 7 Nov 2025 | 31 Oct 2025 | 0.19 MW |
| Forfar WWTW | 7 Nov 2025 | 31 Oct 2025 | 0.2 MW |
| Fofar Solar Farm | 7 Nov 2025 | 31 Oct 2026 | 29.8 MW |
| Cossans Solar/BESS Project | 7 Nov 2025 | 31 Oct 2032 | 49.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2021 | 10 MW |
| 2024 | 19.99 MW |
| 2025 | 49.15 MW |
| 2026 | 185.03 MW |
| 2027 | 212.03 MW |
| 2032 | 261.93 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Lunanhead Battery | 49.9 MW | 0 MW | 30 Sep 2026 | 2 | gate 2 | Consents Approved |
| 2 | Lunanhead Solar Park | 21.8 MW | 49.9 MW | 31 Oct 2026 | 2 | gate 2 | Consents Approved |
| 3 | Montreathmont Moor Forest | 34.38 MW | 71.7 MW | 31 Oct 2026 | 2 | gate 2 | Consents Approved |
| 4 | Lunanhead GSP | 5 MW | 106.08 MW | 26 Oct 2027 | 2 | gate 2 | Consents Approved |
| 5 | North Mains Battery Storage Park | 22 MW | 111.08 MW | 31 Oct 2027 | 2 | gate 2 | Consents Approved |
| 6 | Carsebank PV | 5 MW | 133.08 MW | 30 Nov 2021 | not stated | gate not printed | Consents Approved |
| 7 | Howmuir PV | 5 MW | 138.08 MW | 30 Nov 2021 | not stated | gate not printed | Consents Approved |
| 8 | Orchardbank Battery Storage | 9.99 MW | 143.08 MW | 20 Apr 2024 | not stated | gate not printed | Consents Approved |
| 9 | Forfar Solar - DNO | 27.8 MW | 153.07 MW | 31 Oct 2025 | not stated | gate not printed | Scoping |
| 10 | Tailors Wynd | 0.97 MW | 180.87 MW | 31 Oct 2025 | not stated | gate not printed | Scoping |
| 11 | Exhibit U Marywell Works | 0.19 MW | 181.84 MW | 31 Oct 2025 | not stated | gate not printed | Scoping |
| 12 | Forfar WWTW | 0.2 MW | 182.03 MW | 31 Oct 2025 | not stated | gate not printed | Consents Approved |
| 13 | Fofar Solar Farm | 29.8 MW | 182.23 MW | 31 Oct 2026 | 1 | gate 1 | Scoping |
| 14 | Cossans Solar/BESS Project | 49.9 MW | 212.03 MW | 31 Oct 2032 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2021 | 2 | 10 MW |
| 2024 | 1 | 9.99 MW |
| 2025 | 4 | 29.16 MW |
| 2026 | 4 | 135.88 MW |
| 2027 | 2 | 27 MW |
| 2032 | 1 | 49.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Cossans Solar/BESS Project | Hybrid | 49.9 MW | 31 Oct 2032 | Scoping |
| Lunanhead Battery | Battery storage | 49.9 MW | 30 Sep 2026 | Consents Approved |
| Montreathmont Moor Forest | Hybrid | 34.38 MW | 31 Oct 2026 | Consents Approved |
| Fofar Solar Farm | Solar | 29.8 MW | 31 Oct 2026 | Scoping |
| Forfar Solar - DNO | Solar | 27.8 MW | 31 Oct 2025 | Scoping |
| North Mains Battery Storage Park | Battery storage | 22 MW | 31 Oct 2027 | Consents Approved |
| Lunanhead Solar Park | Solar | 21.8 MW | 31 Oct 2026 | Consents Approved |
| Orchardbank Battery Storage | Battery storage | 9.99 MW | 20 Apr 2024 | Consents Approved |
| Dragonhall Farm PV | Solar | 5 MW | not stated | Built |
| Pressock Farm PV | Solar | 5 MW | not stated | Built |
| Howmuir PV | Solar | 5 MW | 30 Nov 2021 | Consents Approved |
| Lunanhead GSP (Scottish Hydro Electric Power Distribution Plc) | Battery storage | 5 MW | 26 Oct 2027 | Consents Approved |
| Carsebank PV | Solar | 5 MW | 30 Nov 2021 | Consents Approved |
| Pitscandly Farm PV | Solar | 4.13 MW | not stated | Built |
| Tailors Wynd | Solar | 0.97 MW | 31 Oct 2025 | Scoping |
| Forfar WWTW | Solar | 0.2 MW | 31 Oct 2025 | Consents Approved |
| Exhibit U Marywell Works | Gas | 0.19 MW | 31 Oct 2025 | Scoping |