N84 Grid

Mansfield Road BESS

Developer as published, connection site, reference: BOULTBEE BROOKS ENERGY STORAGE LIMITED. Trent Valley South Connection Node B 400kV Substation. (NGET). PRO-004453. Removed from the register (not present in two consecutive files)

Sign in to watch this project
Capacity0 MWBattery storage
Connection date30 Oct 2034Status as printed: Scoping
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

20342035File dated 2025-07-22: connection date 2034-10-30Oct 2034File dated 2026-04-17: connection date 2034-10-3022 Jul202517 Apr2026
20342035File dated 2025-07-22: connection date 2034-10-30Oct 2034File dated 2026-04-17: connection date 2034-10-3022 Jul202517 Apr2026

The connection date is printed the same in every file N84 holds for this project, from 22 Jul 2025 to 17 Apr 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.