Trent Valley South Connection Node B 400kV Substation.

NESO connection site, host NGET.

Contracted here4.87 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,800 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Natpower Thimbleby Green Energy Park31 May 202431 Oct 20331,000 MW
TH Stow Manor31 May 202430 Oct 2034400 MW
Project Number 627 Sep 202430 Oct 2034500 MW
Project Number 831 May 202430 Oct 2034500 MW
Cottam-Ryhall Solar & BESS20 Dec 202430 Oct 2034400 MW
NatPower Allington Green Energy Park20 Dec 202430 Oct 20341,000 MW
Stack Hill Solar and Storage22 Jul 202530 Oct 2034350 MW
Worksop BESS21 Mar 202531 Oct 2034480 MW
Apley Head Farm31 May 202430 Oct 2035240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2033: 1.0 GW2034: 4.6 GW2035: 4.9 GW2033203420354.9 GW
0 MW2.5 GW5.0 GW2033: 1.0 GW2034: 4.6 GW2035: 4.9 GW2033203420354.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20331,000 MW
20344,630 MW
20354,870 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Natpower Thimbleby Green Energy Park1,000 MW0 MW31 Oct 20331gate 1Scoping
2TH Stow Manor400 MW1,000 MW30 Oct 2034not statedgate not printedAwaiting Consents
3Project Number 6500 MW1,400 MW30 Oct 20341gate 1Scoping
4Project Number 8500 MW1,900 MW30 Oct 20341gate 1Scoping
5Cottam-Ryhall Solar & BESS400 MW2,400 MW30 Oct 20341gate 1Scoping
6NatPower Allington Green Energy Park1,000 MW2,800 MW30 Oct 20341gate 1Awaiting Consents
7Stack Hill Solar and Storage350 MW3,800 MW30 Oct 20341gate 1Scoping
8Worksop BESS480 MW4,150 MW31 Oct 20341gate 1Scoping
9Apley Head Farm240 MW4,630 MW30 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203311,000 MW
203473,630 MW
20351240 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Natpower Thimbleby Green Energy ParkBattery storage1,000 MW31 Oct 2033Scoping
NatPower Allington Green Energy ParkBattery storage1,000 MW30 Oct 2034Awaiting Consents
Project Number 6Battery storage500 MW30 Oct 2034Scoping
Project Number 8Battery storage500 MW30 Oct 2034Scoping
Worksop BESSBattery storage480 MW31 Oct 2034Scoping
TH Stow ManorBattery storage400 MW30 Oct 2034Awaiting Consents
Cottam-Ryhall Solar & BESSHybrid400 MW30 Oct 2034Scoping
Stack Hill Solar and StorageHybrid350 MW30 Oct 2034Scoping
Apley Head FarmHybrid240 MW30 Oct 2035Scoping
Mansfield Road BESSBattery storage0 MW30 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.