BRIDGE OF DUN GRID (solar, 28 MW)

Developer as published, connection site, reference: BRIDGE OF DUN GRID. SSEN-1MW-fffd8e437cf6-4.

Sign in to watch this project
Capacity28 MWSolar
Connection date30 Jun 2032Status as printed: Accepted to Connect
MW ahead in N84's order at this site169.33 MWcalculated by N84

Connection date, edition by edition

20322033File dated 2023-09-01: connection date 2032-06-30Jun 2032File dated 2026-10-01: connection date 2032-06-301 Sep20231 Oct2026
20322033File dated 2023-09-01: connection date 2032-06-30Jun 2032File dated 2026-10-01: connection date 2032-06-301 Sep20231 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 1 Sep 2023 to 1 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.