N84 Grid

BRIDGE OF DUN GRID

DNO substation.

Contracted here0.27 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date31 Oct 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue197.33 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BRIDGE OF DUN GRID (solar)25 Sep 201831 Oct 20269.99 MW
BRIDGE OF DUN GRID (solar)12 Nov 202529 Aug 20299.9 MW
BRIDGE OF DUN GRID (bess)24 Feb 202230 Jun 203249.9 MW
BRIDGE OF DUN GRID (solar)25 Jul 202230 Jun 203223.31 MW
BRIDGE OF DUN GRID (bess)5 Apr 202330 Jun 203276.23 MW
BRIDGE OF DUN GRID (solar)1 Aug 202330 Jun 203228 MW
BRIDGE OF DUN (other)18 Jul 202331 Oct 203375 MW
BRIDGE OF DUN 11KV (wind on)6 Nov 202431 Oct 20350.66 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 10 MW2029: 20 MW2032: 197 MW2033: 272 MW2035: 273 MW202620282030203220342035273 MW
0 MW200 MW400 MW2026: 10 MW2029: 20 MW2032: 197 MW2033: 272 MW2035: 273 MW2026202920322035273 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20269.99 MW
202919.89 MW
2032197.33 MW
2033272.33 MW
2035272.99 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BRIDGE OF DUN GRID (solar)9.99 MW0 MW31 Oct 2026not statedgate not printedAccepted to Connect
2BRIDGE OF DUN GRID (solar)9.9 MW9.99 MW29 Aug 2029not statedgate not printedAccepted to Connect
3BRIDGE OF DUN GRID (bess)49.9 MW19.89 MW30 Jun 2032not statedgate not printedAccepted to Connect
4BRIDGE OF DUN GRID (solar)23.31 MW69.79 MW30 Jun 2032not statedgate not printedAccepted to Connect
5BRIDGE OF DUN GRID (bess)76.23 MW93.1 MW30 Jun 2032not statedgate not printedAccepted to Connect
6BRIDGE OF DUN GRID (solar)28 MW169.33 MW30 Jun 2032not statedgate not printedAccepted to Connect
7BRIDGE OF DUN (other)75 MW197.33 MW31 Oct 2033not statedgate not printedAccepted to Connect
8BRIDGE OF DUN 11KV (wind on)0.66 MW272.33 MW31 Oct 2035not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202619.99 MW
202919.9 MW
20324177.44 MW
2033175 MW
203510.66 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BRIDGE OF DUN GRID (other, 75 MW)Other60 MW31 Oct 2033Accepted to Connect
BRIDGE OF DUN GRID (battery, 76.23 MW)Battery storage49.99 MW30 Jun 2032Accepted to Connect
BRIDGE OF DUN GRID (battery, 49.9 MW)Battery storage49.9 MW30 Jun 2032Accepted to Connect
BRIDGE OF DUN GRID (solar, 28 MW)Solar28 MW30 Jun 2032Accepted to Connect
BRIDGE OF DUN GRID (solar, 23.31 MW)Solar16.81 MW30 Jun 2032Accepted to Connect
BRIDGE OF DUN GRID (solar, 9.99 MW)Solar9.99 MW31 Oct 2026Accepted to Connect
BRIDGE OF DUN GRID (solar, 9.9 MW)Solar9.9 MW29 Aug 2029Accepted to Connect
BRIDGE OF DUN GRID (onshore wind, 0.66 MW)Onshore wind0.66 MW31 Oct 2035Accepted to Connect
BRIDGE OF DUN GRID (other, 0.47 MW)Other0.48 MWnot statedConnected
BRIDGE OF DUN GRID (onshore wind, 0.47 MW)Onshore wind0.48 MWnot statedConnected
BRIDGE OF DUN GRID (onshore wind, 0.47 MW)Onshore wind0.48 MWnot statedConnected
BRIDGE OF DUN GRID (other, 0.1 MW)Other0.1 MWnot statedConnected
BRIDGE OF DUN GRID (hydro, 0.1 MW)Hydro and pumped storage0.1 MWnot statedConnected
BRIDGE OF DUN GRID (other, 0.18 MW)Other0.08 MWnot statedConnected
BRIDGE OF DUN GRID (battery, 76.23 MW)Battery storage0 MWnot statedAccepted to Connect
BRIDGE OF DUN GRID (solar, 14.2 MW)Solar0 MWnot statedAccepted to Connect
BRIDGE OF DUN GRID (solar, 25 MW)Solar0 MWnot statedAccepted to Connect
BRIDGE OF DUN GRID (solar, 0.2 MW)Solar0 MW7 Dec 2025Accepted to Connect
BRIDGE OF DUN GRID (battery, 25 MW)Battery storage0 MWnot statedAccepted to Connect
BRIDGE OF DUN GRID (solar, 0.05 MW)Solar0 MWnot statedAccepted to Connect
BRIDGE OF DUN GRID (battery, 25 MW)Battery storage0 MWnot statedAccepted to Connect
BRIDGE OF DUN GRID (solar, 52.68 MW)Solar0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.