N84 Grid

Assel Valley Extension Wind Farm

Developer as published, connection site, reference: Renantis UK Limited. Maybole GSP (SPT). PRO-002632.

Sign in to watch this project
Capacity175 MWHybrid, Gate 1
Connection date30 Oct 2037Status as printed: Scoping
First date seen 30 Oct 2030, difference +2557 dayscalculated by N84
MW ahead in N84's order at this site92.4 MWcalculated by N84

Connection date, edition by edition

Only one edition so far

N84 holds one edition of this register for the project, so there is no earlier date to compare. The chart appears when a later edition is collected.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.