N84 Grid

Maybole GSP

NESO connection site, host SPT.

Contracted here0.31 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Sep 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue305.8 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Craiginmoddie Wind Farm31 May 202430 Sep 203192.4 MW
Assel Valley Extension Wind Farm31 May 202431 Oct 203288 MW
Craigdow Hill Wind Farm22 Jul 202531 Oct 203238.4 MW
Assel Valley Extension Wind Farm31 May 202430 Oct 203787 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2031: 92 MW2032: 219 MW2037: 306 MW2031203220332034203520362037306 MW
0 MW200 MW400 MW2031: 92 MW2032: 219 MW2037: 306 MW2031203320352037306 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203192.4 MW
2032218.8 MW
2037305.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Craiginmoddie Wind Farm92.4 MW0 MW30 Sep 20311gate 1Scoping
2Assel Valley Extension Wind Farm88 MW92.4 MW31 Oct 20321gate 1Scoping
3Craigdow Hill Wind Farm38.4 MW180.4 MW31 Oct 20321gate 1Scoping
4Assel Valley Extension Wind Farm87 MW218.8 MW30 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2031192.4 MW
20322126.4 MW
2037187 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Assel Valley Extension Wind FarmHybrid175 MW30 Oct 2037Scoping
Hadyard HillOnshore wind99.9 MWnot statedBuilt
Craiginmoddie Wind FarmOnshore wind92.4 MW30 Sep 2031Scoping
Craigdow Hill Wind FarmOnshore wind38.4 MW31 Oct 2032Scoping
Assel Valley Wind FarmOnshore wind29.95 MWnot statedBuilt
Kirk HillOnshore wind20 MWnot statedBuilt
Girvan Mains AD PlantBiomass and waste0.25 MWnot statedBuilt