N84 Grid

Kirkby (HD001KIR LTD)

Developer as published, connection site, reference: HD001KIR LTD. Kirkby 275kV Substation (NGET). PRO-001084.

Sign in to watch this project
Capacity57 MWBattery storage
Connection date30 Oct 2037Status as printed: Consents Approved
First date seen 30 Sep 2025, difference +4413 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

Only one edition so far

N84 holds one edition of this register for the project, so there is no earlier date to compare. The chart appears when a later edition is collected.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1178Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1158
  2. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1177Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1157

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.