Kirkby 275kV Substation

NESO connection site, host NGET.

Contracted here0.51 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Aug 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue514 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Kirkby31 May 202431 Oct 202749.9 MW
Kirkby (Tertiary)31 May 202430 Aug 202757 MW
Kirkby Green Energy Centre31 May 202430 Oct 2028400 MW
Kirkby31 May 202430 Oct 20377.1 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2027: 107 MW2028: 507 MW2037: 514 MW202720292031203320352037514 MW
0 MW400 MW800 MW2027: 107 MW2028: 507 MW2037: 514 MW2027203020332037514 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027106.9 MW
2028506.9 MW
2037514 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Kirkby49.9 MW0 MW31 Oct 20272gate 2Consents Approved
2Kirkby (Tertiary)57 MW49.9 MW30 Aug 20271gate 1Scoping
3Kirkby Green Energy Centre400 MW106.9 MW30 Oct 20281gate 1Scoping
4Kirkby7.1 MW506.9 MW30 Oct 2037not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20272106.9 MW
20281400 MW
203717.1 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Kirkby Green Energy CentreHybrid400 MW30 Oct 2028Scoping
Kirkby (HD001KIR LTD)Battery storage57 MW30 Oct 2037Consents Approved
Kirkby (Tertiary)Hybrid57 MW30 Aug 2027Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.