Developer as published, connection site, reference: CSE23 LIMITED. Fleet 400kV Substation (NGET). PRO-001087.

Sign in to watch this project
Capacity47.5 MWSolar, Gate 2
Connection date30 Jul 2029Status as printed: Consents Approved
First date seen 31 Oct 2025, difference +1368 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20262027202820292030File dated 2026-09-11: connection date 2026-10-31Oct 2026File dated 2026-10-20: connection date 2029-07-30Jul 202911 Sep202620 Oct2026
20262027202820292030File dated 2026-09-11: connection date 2026-10-31Oct 2026File dated 2026-10-20: connection date 2029-07-30Jul 202911 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 815Receipt: NESO TEC Register, file dated 11 Sep 2026, row 794
  2. 20 Oct 2026. MW Effective From printed as 30 Jul 2029 (previous file: 31 Oct 2026), 1,003 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +1003 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 815Receipt: NESO TEC Register, file dated 11 Sep 2026, row 794

Supported by National Energy SO Open Data