N84 Grid

Fleet 400kV Substation

NESO connection site, host NGET.

Contracted here0.20 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date13 Jan 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue199.5 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Fleet (Tertiary)31 May 202430 Jul 202947.5 MW
Fleet EGH (Tertiary)31 May 202413 Jan 202747.5 MW
Fleet Tertiary31 May 20247 Aug 202847.5 MW
Fleet Solar PV31 May 20247 Aug 202857 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 48 MW2028: 152 MW2029: 200 MW202720282029200 MW
0 MW100 MW200 MW2027: 48 MW2028: 152 MW2029: 200 MW202720282029200 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202747.5 MW
2028152 MW
2029199.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Fleet (Tertiary)47.5 MW0 MW30 Jul 20292gate 2Consents Approved
2Fleet EGH (Tertiary)47.5 MW47.5 MW13 Jan 2027not statedgate not printedConsents Approved
3Fleet Tertiary47.5 MW95 MW7 Aug 20281gate 1Scoping
4Fleet Solar PV57 MW142.5 MW7 Aug 2028not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027147.5 MW
20282104.5 MW
2029147.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Fleet Solar PVSolar57 MW7 Aug 2028Awaiting Consents
Fleet (Tertiary)Solar47.5 MW30 Jul 2029Consents Approved
Fleet EGH (Tertiary)Hybrid47.5 MW13 Jan 2027Consents Approved
Fleet TertiaryThermal47.5 MW7 Aug 2028Scoping
Peak Gen BracknellGas20 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.