Capenhurst (ENSO GREEN HOLDINGS Q LIMITED)

Developer as published, connection site, reference: ENSO GREEN HOLDINGS Q LIMITED. Capenhurst 275kV Substation (NGET). PRO-000540.

Sign in to watch this project
Capacity400 MWHybrid, Gate 1
Connection date14 Sep 2033Status as printed: Scoping
First date seen 31 Oct 2025, difference +2875 dayscalculated by N84
MW ahead in N84's order at this site57 MWcalculated by N84

Connection date, edition by edition

20332034File dated 2026-09-11: connection date 2033-09-30Sep 2033File dated 2026-10-20: connection date 2033-09-14Sep 203311 Sep202620 Oct2026
20332034File dated 2026-09-11: connection date 2033-09-30Sep 2033File dated 2026-10-20: connection date 2033-09-14Sep 203311 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 14 Sep 2033 (previous file: 30 Sep 2033), 16 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -16 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 349Receipt: NESO TEC Register, file dated 11 Sep 2026, row 344

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.