N84 Grid

Capenhurst 275kV Substation

NESO connection site, host NGET.

Contracted here0.90 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue896.6 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Capenhurst Tertiary20 Dec 202431 Oct 202757 MW
Capenhurst31 May 202414 Sep 2033400 MW
Hill Farm31 May 202430 Oct 2035240 MW
Mill Hey_Capenhurst BESS22 Jul 202530 Oct 2037199.6 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2027: 57 MW2033: 457 MW2035: 697 MW2037: 897 MW202720292031203320352037897 MW
0 MW500 MW1.0 GW2027: 57 MW2033: 457 MW2035: 697 MW2037: 897 MW2027203020332037897 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202757 MW
2033457 MW
2035697 MW
2037896.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Capenhurst Tertiary57 MW0 MW31 Oct 20271gate 1Scoping
2Capenhurst400 MW57 MW14 Sep 20331gate 1Scoping
3Hill Farm240 MW457 MW30 Oct 20351gate 1Scoping
4Mill Hey_Capenhurst BESS199.6 MW697 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027157 MW
20331400 MW
20351240 MW
20371199.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Capenhurst (ENSO GREEN HOLDINGS Q LIMITED)Hybrid400 MW14 Sep 2033Scoping
Hill FarmBattery storage240 MW30 Oct 2035Scoping
Mill Hey_Capenhurst BESSBattery storage199.6 MW30 Oct 2037Scoping
Capenhurst 275KV Substation (ZENOBE CAPENHURST LIMITED)Battery storage100 MWnot statedBuilt
CheshireGas90 MWnot statedBuilt
Capenhurst Tertiary ConnectionBattery storage57 MWnot statedBuilt
Capenhurst TertiaryHybrid57 MW31 Oct 2027Scoping
Native River (Capenhurst)Battery storage57 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.