Capacity45 MWHybrid, Gate 2
Connection date31 Jul 2026Status as printed: Consents Approved
MW ahead in N84's order at this site49.9 MWcalculated by N84
Connection date, edition by edition
No date history to draw
The files N84 holds in your history window print no connection date for this project.
Observed changes
N84 holds 2 editions of the NESO Embedded Register back to 7 Nov 2025. No change for this record is older than 30 days.
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Customer name printed as Loch Fergus Solar Ltd (previous file: Lochfergus Solar LTD). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedLochfergus Solar LTD → Loch Fergus Solar LtdReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 353Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 352
- 20 Oct 2026. Connection site printed as Ayr 275/33kV (previous file: Lochfergus Solar Substation 33kV). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedLochfergus Solar Substation 33kV → Ayr 275/33kVReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 353Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 352
- 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO Embedded Register, file dated 20 Oct 2026, row 353Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 352
- 20 Oct 2026. MW Effective From printed as 31 Jul 2026 (previous file: blank). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 353Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 352
Supported by National Energy SO Open Data