N84 Grid

Ayr 275/33kV

NESO connection site, host SPT.

Contracted here0.70 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Jul 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue704.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Holmston Farm Battery Energy Storage System31 May 202431 Jul 202649.9 MW
Loch Fergus Solar7 Nov 202531 Jul 202645 MW
Ayr Energy Storage31 May 202430 Oct 2028150 MW
Knockkippen Energy Park31 May 202430 Aug 202860 MW
Clonmacate Farm BESS31 May 202431 Oct 2030200 MW
FPE Ayr BESS22 Jul 202530 Oct 2037200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2026: 95 MW2028: 305 MW2030: 505 MW2037: 705 MW202620282030203220342037705 MW
0 MW400 MW800 MW2026: 95 MW2028: 305 MW2030: 505 MW2037: 705 MW20262029203220352037705 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202694.9 MW
2028304.9 MW
2030504.9 MW
2037704.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Holmston Farm Battery Energy Storage System49.9 MW0 MW31 Jul 20262gate 2Under Construction/Commissioning
2Loch Fergus Solar45 MW49.9 MW31 Jul 20262gate 2Consents Approved
3Ayr Energy Storage150 MW94.9 MW30 Oct 20282gate 2Consents Approved
4Knockkippen Energy Park60 MW244.9 MW30 Aug 2028not statedgate not printedScoping
5Clonmacate Farm BESS200 MW304.9 MW31 Oct 2030not statedgate not printedScoping
6FPE Ayr BESS200 MW504.9 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026294.9 MW
20282210 MW
20301200 MW
20371200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
FPE Ayr BESSBattery storage200 MW30 Oct 2037Scoping
Clonmacate Farm BESSBattery storage200 MW31 Oct 2030Scoping
Ayr Energy StorageBattery storage150 MW30 Oct 2028Consents Approved
Knockkippen Energy ParkHybrid60 MW30 Aug 2028Scoping
Holmston Farm Battery Energy Storage SystemBattery storage49.9 MW31 Jul 2026Under Construction/Commissioning
Loch Fergus SolarHybrid45 MW31 Jul 2026Consents Approved
Ayrshire College HydroHydro and pumped storage0.1 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.