The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Holmston Farm Battery Energy Storage System
31 May 2024 to 31 Jul 2026, date already passed (gate 2) - Loch Fergus Solar
7 Nov 2025 to 31 Jul 2026, date already passed (gate 2) - Ayr Energy Storage
31 May 2024 to 30 Oct 2028 (gate 2) - Knockkippen Energy Park
31 May 2024 to 30 Aug 2028 (gate not printed) - Clonmacate Farm BESS
31 May 2024 to 31 Oct 2030 (gate not printed) - FPE Ayr BESS
22 Jul 2025 to 30 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Holmston Farm Battery Energy Storage System | 31 May 2024 | 31 Jul 2026 | 49.9 MW |
| Loch Fergus Solar | 7 Nov 2025 | 31 Jul 2026 | 45 MW |
| Ayr Energy Storage | 31 May 2024 | 30 Oct 2028 | 150 MW |
| Knockkippen Energy Park | 31 May 2024 | 30 Aug 2028 | 60 MW |
| Clonmacate Farm BESS | 31 May 2024 | 31 Oct 2030 | 200 MW |
| FPE Ayr BESS | 22 Jul 2025 | 30 Oct 2037 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 94.9 MW |
| 2028 | 304.9 MW |
| 2030 | 504.9 MW |
| 2037 | 704.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Holmston Farm Battery Energy Storage System | 49.9 MW | 0 MW | 31 Jul 2026 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Loch Fergus Solar | 45 MW | 49.9 MW | 31 Jul 2026 | 2 | gate 2 | Consents Approved |
| 3 | Ayr Energy Storage | 150 MW | 94.9 MW | 30 Oct 2028 | 2 | gate 2 | Consents Approved |
| 4 | Knockkippen Energy Park | 60 MW | 244.9 MW | 30 Aug 2028 | not stated | gate not printed | Scoping |
| 5 | Clonmacate Farm BESS | 200 MW | 304.9 MW | 31 Oct 2030 | not stated | gate not printed | Scoping |
| 6 | FPE Ayr BESS | 200 MW | 504.9 MW | 30 Oct 2037 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 2 | 94.9 MW |
| 2028 | 2 | 210 MW |
| 2030 | 1 | 200 MW |
| 2037 | 1 | 200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| FPE Ayr BESS | Battery storage | 200 MW | 30 Oct 2037 | Scoping |
| Clonmacate Farm BESS | Battery storage | 200 MW | 31 Oct 2030 | Scoping |
| Ayr Energy Storage | Battery storage | 150 MW | 30 Oct 2028 | Consents Approved |
| Knockkippen Energy Park | Hybrid | 60 MW | 30 Aug 2028 | Scoping |
| Holmston Farm Battery Energy Storage System | Battery storage | 49.9 MW | 31 Jul 2026 | Under Construction/Commissioning |
| Loch Fergus Solar | Hybrid | 45 MW | 31 Jul 2026 | Consents Approved |
| Ayrshire College Hydro | Hydro and pumped storage | 0.1 MW | not stated | Built |