THURSO (hydro, 30 MW)

Developer as published, connection site, reference: THURSO. SSEN-1MW-205692cd8867-2.

Sign in to watch this project
Capacity30 MWHydro and pumped storage
Connection date21 Feb 2029Status as printed: Accepted to Connect
MW ahead in N84's order at this site159.6 MWcalculated by N84

Connection date, edition by edition

20292030File dated 2024-02-01: connection date 2029-02-21Feb 2029File dated 2026-10-01: connection date 2029-02-211 Feb20241 Oct2026
20292030File dated 2024-02-01: connection date 2029-02-21Feb 2029File dated 2026-10-01: connection date 2029-02-211 Feb20241 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 1 Feb 2024 to 1 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.