Medway 3 Power Station

Developer as published, connection site, reference: MEDWAY POWER LIMITED. Kingsnorth 400kV Substation (NGET). PRO-002578.

Sign in to watch this project
Capacity500 MWBattery storage, Gate 1
Connection date30 Apr 2032Status as printed: Scoping
First date seen 31 Dec 2030, difference +486 dayscalculated by N84
MW ahead in N84's order at this site4,029.5 MWcalculated by N84

Connection date, edition by edition

2030203120322033File dated 2026-09-11: connection date 2030-12-31Dec 2030File dated 2026-10-20: connection date 2032-04-30Apr 203211 Sep202620 Oct2026
2030203120322033File dated 2026-09-11: connection date 2030-12-31Dec 2030File dated 2026-10-20: connection date 2032-04-30Apr 203211 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 30 Apr 2032 (previous file: 31 Dec 2030), 486 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +486 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1387Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1366