N84 Grid

Kingsnorth 400kV Substation

NESO connection site, host NGET.

Contracted here4.53 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 May 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue4,029.5 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Cuxton 49.5MW BESS31 May 202431 May 202349.5 MW
Rochester Renewable Project31 May 202422 Sep 202860 MW
Kingsnorth31 May 202431 Oct 2028120 MW
Gridlink Interconnector15 Feb 202231 Mar 20291,500 MW
Damhead Creek 231 May 202431 Oct 20301,800 MW
Kingsnorth BESS NP31 May 202431 Dec 2030500 MW
Medway 3 Power Station31 May 202430 Apr 2032500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.5 GW5.0 GW2023: 50 MW2028: 230 MW2029: 1.7 GW2030: 4.0 GW2032: 4.5 GW2023202520272029203120324.5 GW
0 MW2.5 GW5.0 GW2023: 50 MW2028: 230 MW2029: 1.7 GW2030: 4.0 GW2032: 4.5 GW20232026202920324.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202349.5 MW
2028229.5 MW
20291,729.5 MW
20304,029.5 MW
20324,529.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Cuxton 49.5MW BESS49.5 MW0 MW31 May 2023not statedgate not printedConsents Approved
2Rochester Renewable Project60 MW49.5 MW22 Sep 2028not statedgate not printedScoping
3Kingsnorth120 MW109.5 MW31 Oct 20281gate 1Scoping
4Gridlink Interconnector1,500 MW229.5 MW31 Mar 2029not statedgate not printedScoping
5Damhead Creek 21,800 MW1,729.5 MW31 Oct 2030not statedgate not printedConsents Approved
6Kingsnorth BESS NP500 MW3,529.5 MW31 Dec 20301gate 1Scoping
7Medway 3 Power Station500 MW4,029.5 MW30 Apr 20321gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2023149.5 MW
20282180 MW
202911,500 MW
203022,300 MW
20321500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Damhead Creek 2Hybrid1,800 MW31 Oct 2030Consents Approved
Gridlink InterconnectorInterconnector1,500 MW31 Mar 2029Scoping
Damhead CreekGas812 MWnot statedBuilt
Medway 3 Power StationBattery storage500 MW30 Apr 2032Scoping
Kingsnorth BESS NPBattery storage500 MW31 Dec 2030Scoping
Kingsnorth (ENSO GREEN HOLDINGS G LIMITED)Hybrid120 MW31 Oct 2028Scoping
Rochester Renewable ProjectHybrid60 MW22 Sep 2028Scoping
Cuxton 49.5MW BESSBattery storage49.5 MW31 May 2023Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.