Capacity200 MWBattery storage, Gate 2
Connection date31 May 2029Status as printed: Under Construction/Commissioning
First date seen 30 Nov 2026, difference +913 dayscalculated by N84
First date seen 30 Nov 2026, difference +913 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84
Connection date, edition by edition
Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Project Status printed as Under Construction/Commissioning (previous file: Scoping). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Under Construction/CommissioningReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1422Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1402
- 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1422Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1402
- 20 Oct 2026. MW Effective From printed as 31 May 2029 (previous file: 30 Nov 2026), 913 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +913 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1422Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1402
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.