N84 Grid

Middleton 400KV Substation

NESO connection site, host NGET.

Contracted here0.84 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue840 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Middleton BESS31 May 202431 May 2029200 MW
Heysham Green Energy Centre31 May 202430 Oct 2028400 MW
Lightsource Middleton20 Dec 202430 Oct 2037240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2028: 400 MW2029: 600 MW2037: 840 MW202820302032203420362037840 MW
0 MW500 MW1.0 GW2028: 400 MW2029: 600 MW2037: 840 MW2028203120342037840 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028400 MW
2029600 MW
2037840 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Middleton BESS200 MW0 MW31 May 20292gate 2Under Construction/Commissioning
2Heysham Green Energy Centre400 MW200 MW30 Oct 2028not statedgate not printedAwaiting Consents
3Lightsource Middleton240 MW600 MW30 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281400 MW
20291200 MW
20371240 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Heysham Green Energy CentreHybrid400 MW30 Oct 2028Awaiting Consents
Lightsource MiddletonHybrid240 MW30 Oct 2037Scoping
Middleton BESSBattery storage200 MW31 May 2029Under Construction/Commissioning

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.