N84 Grid

Great Coates BESS

Developer as published, connection site, reference: BRUTON ONE BESS LIMITED. Grimsby West 400kV Substation (NGET). PRO-003960.

Sign in to watch this project
Capacity300 MWBattery storage, Gate 1
Connection date31 Oct 2031Status as printed: Scoping
First date seen 31 Oct 2033, difference -731 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

2031203220332034File dated 2026-09-11: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2031-10-31Oct 203111 Sep202620 Oct2026
2031203220332034File dated 2026-09-11: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2031-10-31Oct 203111 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2031 (previous file: 31 Oct 2033), 731 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -731 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 920Receipt: NESO TEC Register, file dated 11 Sep 2026, row 899

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.