Grimsby West 400kV Substation

NESO connection site, host NGET.

Contracted here6.89 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,955 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Great Coates BESS31 May 202431 Oct 2031300 MW
EcoGrimsbyWest31 May 202430 Oct 2033249 MW
Carbon Free 203031 May 202430 Jun 2034500 MW
Stallingborough PV & BESS Station31 May 202430 Oct 2034500 MW
Grimsby BESS31 May 202430 Apr 2035500 MW
STALLINGBOROUGH CARBON CAPTURE CCGT31 May 202430 May 2035906 MW
Bute Hydrogen Project 331 May 202430 Oct 20353,600 MW
North Ray Solar Farm 222 Jul 202530 Oct 2035180 MW
West Grimsby Farm31 May 202431 Oct 2035150 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2031: 300 MW2033: 549 MW2034: 1.5 GW2035: 6.9 GW203120322033203420356.9 GW
0 MW4.0 GW8.0 GW2031: 300 MW2033: 549 MW2034: 1.5 GW2035: 6.9 GW2031203320356.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031300 MW
2033549 MW
20341,549 MW
20356,885 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Great Coates BESS300 MW0 MW31 Oct 20311gate 1Scoping
2EcoGrimsbyWest249 MW300 MW30 Oct 2033not statedgate not printedScoping
3Carbon Free 2030500 MW549 MW30 Jun 2034not statedgate not printedScoping
4Stallingborough PV & BESS Station500 MW1,049 MW30 Oct 2034not statedgate not printedScoping
5Grimsby BESS500 MW1,549 MW30 Apr 20351gate 1Scoping
6STALLINGBOROUGH CARBON CAPTURE CCGT906 MW2,049 MW30 May 2035not statedgate not printedScoping
7Bute Hydrogen Project 33,600 MW2,955 MW30 Oct 20351gate 1Scoping
8North Ray Solar Farm 2180 MW6,555 MW30 Oct 20351gate 1Scoping
9West Grimsby Farm150 MW6,735 MW31 Oct 20351gate 1Awaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311300 MW
20331249 MW
203421,000 MW
203555,336 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bute Hydrogen Project 3Gas3,600 MW30 Oct 2035Scoping
STALLINGBOROUGH CARBON CAPTURE CCGTGas906 MW30 May 2035Scoping
Carbon Free 2030Hybrid500 MW30 Jun 2034Scoping
Stallingborough PV & BESS StationHybrid500 MW30 Oct 2034Scoping
Grimsby BESSBattery storage500 MW30 Apr 2035Scoping
Great Coates BESSBattery storage300 MW31 Oct 2031Scoping
EcoGrimsbyWestHybrid249 MW30 Oct 2033Scoping
North Ray Solar Farm 2Solar180 MW30 Oct 2035Scoping
West Grimsby FarmSolar150 MW31 Oct 2035Awaiting Consents
GrimsbyGas40 MWnot statedBuilt

Supported by National Energy SO Open Data