PARK NORTH (gas)

Developer as published, connection site, reference: PARK NORTH. SSEN-1MW-09da719ecf9f. Not in the latest file

Sign in to watch this project
Capacity0 MWGas
Connection date15 Aug 2025Status as printed: Accepted to Connect
MW ahead in N84's order at this siteNot calculatedN84 orders only projects at a NESO connection site with a printed date.

Connection date, edition by edition

20252026File dated 2023-08-01: connection date 2025-08-15Aug 2025File dated 2026-09-01: connection date 2025-08-151 Aug20231 Sep2026
20252026File dated 2023-08-01: connection date 2025-08-15Aug 2025File dated 2026-09-01: connection date 2025-08-151 Aug20231 Sep2026

The connection date is printed the same in every file N84 holds for this project, from 1 Aug 2023 to 1 Sep 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 1 Oct 2026. Not printed in this file; printed in the previous one. Between the files dated 1 Sep 2026 and 1 Oct 2026.present → missingReceipt: SSEN Embedded Capacity Register, file dated 1 Oct 2026Receipt: SSEN Embedded Capacity Register, file dated 1 Sep 2026, row 2302

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.