Bradenham - Thetford (Necton) GEC (Ethos Green)

Developer as published, connection site, reference: NECTON GREEN ENERGY CENTRE LTD. Necton 400kV Substation (NGET). PRO-004346.

Sign in to watch this project
Capacity850 MWHybrid, Gate 1
Connection date1 Oct 2033Status as printed: Scoping
MW ahead in N84's order at this site2,718 MWcalculated by N84

Connection date, edition by edition

20332034File dated 2024-05-31: connection date 2033-10-01Oct 2033File dated 2026-10-20: connection date 2033-10-0131 May202420 Oct2026
20332034File dated 2024-05-31: connection date 2033-10-01Oct 2033File dated 2026-10-20: connection date 2033-10-0131 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data