The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Vanguard
31 May 2024 to 31 Dec 2027 (gate 2) - Vanguard
31 May 2024 to 1 Apr 2028 (gate 2) - Norfolk Boreas
31 May 2024 to 1 Oct 2029 (gate not printed) - Norfolk Boreas
31 May 2024 to 31 Dec 2030 (gate not printed) - Necton Greener Grid Park
31 May 2024 to 31 Oct 2032 (gate not printed) - Bradenham - Thetford (Necton) GEC (Ethos Green)
31 May 2024 to 1 Oct 2033 (gate 1) - Zenobe Necton BESS
31 May 2024 to 31 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Vanguard | 31 May 2024 | 31 Dec 2027 | 400 MW |
| Vanguard | 31 May 2024 | 1 Apr 2028 | 920 MW |
| Norfolk Boreas | 31 May 2024 | 1 Oct 2029 | 400 MW |
| Norfolk Boreas | 31 May 2024 | 31 Dec 2030 | 920 MW |
| Necton Greener Grid Park | 31 May 2024 | 31 Oct 2032 | 78 MW |
| Bradenham - Thetford (Necton) GEC (Ethos Green) | 31 May 2024 | 1 Oct 2033 | 850 MW |
| Zenobe Necton BESS | 31 May 2024 | 31 Oct 2034 | 300 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 400 MW |
| 2028 | 1,320 MW |
| 2029 | 1,720 MW |
| 2030 | 2,640 MW |
| 2032 | 2,718 MW |
| 2033 | 3,568 MW |
| 2034 | 3,868 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Vanguard | 400 MW | 0 MW | 31 Dec 2027 | 2 | gate 2 | Consents Approved |
| 2 | Vanguard | 920 MW | 400 MW | 1 Apr 2028 | 2 | gate 2 | Scoping |
| 3 | Norfolk Boreas | 400 MW | 1,320 MW | 1 Oct 2029 | not stated | gate not printed | Awaiting Consents |
| 4 | Norfolk Boreas | 920 MW | 1,720 MW | 31 Dec 2030 | not stated | gate not printed | Scoping |
| 5 | Necton Greener Grid Park | 78 MW | 2,640 MW | 31 Oct 2032 | not stated | gate not printed | Awaiting Consents |
| 6 | Bradenham - Thetford (Necton) GEC (Ethos Green) | 850 MW | 2,718 MW | 1 Oct 2033 | 1 | gate 1 | Scoping |
| 7 | Zenobe Necton BESS | 300 MW | 3,568 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 400 MW |
| 2028 | 1 | 920 MW |
| 2029 | 1 | 400 MW |
| 2030 | 1 | 920 MW |
| 2032 | 1 | 78 MW |
| 2033 | 1 | 850 MW |
| 2034 | 1 | 300 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Norfolk Boreas | Offshore wind | 1,320 MW | 31 Dec 2030 | Scoping |
| Vanguard | Offshore wind | 1,320 MW | 1 Apr 2028 | Scoping |
| Bradenham - Thetford (Necton) GEC (Ethos Green) | Hybrid | 850 MW | 1 Oct 2033 | Scoping |
| Dudgeon Offshore Wind Farm | Offshore wind | 400 MW | not stated | Built |
| Zenobe Necton BESS | Battery storage | 300 MW | 31 Oct 2034 | Scoping |
| Necton Greener Grid Park | Battery storage | 78 MW | 31 Oct 2032 | Awaiting Consents |
Supported by National Energy SO Open Data