N84 Grid

Necton 400kV Substation

NESO connection site, host NGET.

Contracted here3.87 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Dec 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,568 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Vanguard31 May 202431 Dec 2027400 MW
Vanguard31 May 20241 Apr 2028920 MW
Norfolk Boreas31 May 20241 Oct 2029400 MW
Norfolk Boreas31 May 202431 Dec 2030920 MW
Necton Greener Grid Park31 May 202431 Oct 203278 MW
Bradenham - Thetford (Necton) GEC (Ethos Green)31 May 20241 Oct 2033850 MW
Zenobe Necton BESS31 May 202431 Oct 2034300 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2027: 400 MW2028: 1.3 GW2029: 1.7 GW2030: 2.6 GW2032: 2.7 GW2033: 3.6 GW2034: 3.9 GW202720282029203020312032203320343.9 GW
0 MW2.0 GW4.0 GW2027: 400 MW2028: 1.3 GW2029: 1.7 GW2030: 2.6 GW2032: 2.7 GW2033: 3.6 GW2034: 3.9 GW20272029203120343.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027400 MW
20281,320 MW
20291,720 MW
20302,640 MW
20322,718 MW
20333,568 MW
20343,868 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Vanguard400 MW0 MW31 Dec 20272gate 2Consents Approved
2Vanguard920 MW400 MW1 Apr 20282gate 2Scoping
3Norfolk Boreas400 MW1,320 MW1 Oct 2029not statedgate not printedAwaiting Consents
4Norfolk Boreas920 MW1,720 MW31 Dec 2030not statedgate not printedScoping
5Necton Greener Grid Park78 MW2,640 MW31 Oct 2032not statedgate not printedAwaiting Consents
6Bradenham - Thetford (Necton) GEC (Ethos Green)850 MW2,718 MW1 Oct 20331gate 1Scoping
7Zenobe Necton BESS300 MW3,568 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20271400 MW
20281920 MW
20291400 MW
20301920 MW
2032178 MW
20331850 MW
20341300 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Norfolk BoreasOffshore wind1,320 MW31 Dec 2030Scoping
VanguardOffshore wind1,320 MW1 Apr 2028Scoping
Bradenham - Thetford (Necton) GEC (Ethos Green)Hybrid850 MW1 Oct 2033Scoping
Dudgeon Offshore Wind FarmOffshore wind400 MWnot statedBuilt
Zenobe Necton BESSBattery storage300 MW31 Oct 2034Scoping
Necton Greener Grid ParkBattery storage78 MW31 Oct 2032Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.