Berryhill Solar Farm

Developer as published, connection site, reference: BERRYHILL SOLAR FARM LIMITED. Charleston GSP (SHET). PRO-001679.

Sign in to watch this project
Capacity45 MWSolar, Gate 2
Connection date31 Jul 2027Status as printed: Consents Approved
MW ahead in N84's order at this site20 MWcalculated by N84

Connection date, edition by edition

No date history to draw

The files N84 holds in your history window print no connection date for this project.

Observed changes

N84 holds 2 editions of the NESO Embedded Register back to 7 Nov 2025. No change for this record is older than 30 days.

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Project Status printed as Consents Approved (previous file: Scoping). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedScoping → Consents ApprovedReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 59Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 59
  2. 20 Oct 2026. Gate printed as 2 (previous file: blank). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 2Receipt: NESO Embedded Register, file dated 20 Oct 2026, row 59Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 59
  3. 20 Oct 2026. MW Effective From printed as 31 Jul 2027 (previous file: blank). N84 holds no copy between 7 Nov 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedReceipt: NESO Embedded Register, file dated 20 Oct 2026, row 59Receipt: NESO Embedded Register, file dated 7 Nov 2025, row 59

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.