N84 Grid

Charleston GSP

NESO connection site, host SHET.

Contracted here0.19 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date30 Mar 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue185.15 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Charleston Solar PV7 Nov 202530 Mar 202720 MW
Berryhill Solar Farm7 Nov 202531 Jul 202745 MW
Burnside Battery Storage Park7 Nov 202531 Oct 202749.9 MW
Stoneygroves PV22 Jul 202530 Oct 203120 MW
Lyndhurst Camperdown BESS22 Jul 202531 Oct 203149.5 MW
Charleston GSP (James Hutton Institute PV)7 Nov 202531 Oct 20310.75 MW
Harris Academy7 Nov 202531 Oct 20310.13 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2027: 115 MW2031: 185 MW20272028202920302031185 MW
0 MW100 MW200 MW2027: 115 MW2031: 185 MW202720292031185 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027114.9 MW
2031185.28 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Charleston Solar PV20 MW0 MW30 Mar 20272gate 2Scoping
2Berryhill Solar Farm45 MW20 MW31 Jul 20272gate 2Consents Approved
3Burnside Battery Storage Park49.9 MW65 MW31 Oct 20271gate 1Awaiting Consents
4Stoneygroves PV20 MW114.9 MW30 Oct 20311gate 1Scoping
5Lyndhurst Camperdown BESS49.5 MW134.9 MW31 Oct 20311gate 1Scoping
6Charleston GSP (James Hutton Institute PV)0.75 MW184.4 MW31 Oct 2031not statedgate not printedScoping
7Harris Academy0.13 MW185.15 MW31 Oct 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20273114.9 MW
2031470.38 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Burnside Battery Storage ParkBattery storage49.9 MW31 Oct 2027Awaiting Consents
West Gourdie BatteryBattery storage49.9 MWnot statedBuilt
Lyndhurst Camperdown BESSBattery storage49.5 MW31 Oct 2031Scoping
Berryhill Solar FarmSolar45 MW31 Jul 2027Consents Approved
Stoneygroves PVSolar20 MW30 Oct 2031Scoping
Charleston Solar PVSolar20 MW30 Mar 2027Scoping
Charleston GSP (James Hutton Institute PV)Battery storage0.75 MW31 Oct 2031Scoping
Harris AcademySolar0.13 MW31 Oct 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.