FASNAKYLE GRID (onshore wind, 62.4 MW)

Developer as published, connection site, reference: FASNAKYLE GRID. SSEN-1MW-39fca059029d-2.

Sign in to watch this project
Capacity62.4 MWOnshore wind
Connection date30 Sep 2031Status as printed: Accepted to Connect
MW ahead in N84's order at this site50 MWcalculated by N84

Connection date, edition by edition

20312032File dated 2025-07-01: connection date 2031-09-30Sep 2031File dated 2026-10-01: connection date 2031-09-301 Jul20251 Oct2026
20312032File dated 2025-07-01: connection date 2031-09-30Sep 2031File dated 2026-10-01: connection date 2031-09-301 Jul20251 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 1 Jul 2025 to 1 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.