Petroc Offshore Wind Farm

Developer as published, connection site, reference: BLUEFLOAT ENERGY UK HOLDINGS LIMITED. Alverdiscott 400kV Substation (NGET). PRO-001661.

Sign in to watch this project
Capacity300 MWOffshore wind, Gate 1
Connection date31 Mar 2026Status as printed: Scoping
First date seen 31 Mar 2029, difference -1096 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20262027202820292030File dated 2026-09-11: connection date 2029-03-31Mar 2029File dated 2026-10-20: connection date 2026-03-31Mar 202611 Sep202620 Oct2026
20262027202820292030File dated 2026-09-11: connection date 2029-03-31Mar 2029File dated 2026-10-20: connection date 2026-03-31Mar 202611 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Mar 2026 (previous file: 31 Mar 2029), 1,096 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -1096 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 1682Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1656

Supported by National Energy SO Open Data