Biggleswade PV

Developer as published, connection site, reference: CSE38 LIMITED. Biggleswade 400kV Substation (NGET). PRO-002226.

Sign in to watch this project
Capacity49.9 MWHybrid, Gate 1
Connection date31 Oct 2031Status as printed: Awaiting Consents
MW ahead in N84's order at this site57 MWcalculated by N84

Connection date, edition by edition

20312032File dated 2024-12-20: connection date 2031-10-31Oct 2031File dated 2026-10-20: connection date 2031-10-3120 Dec202420 Oct2026
20312032File dated 2024-12-20: connection date 2031-10-31Oct 2031File dated 2026-10-20: connection date 2031-10-3120 Dec202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 20 Dec 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.