N84 Grid

Biggleswade 400kV Substation

NESO connection site, host NGET.

Contracted here3.06 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date28 Sep 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,806.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Biggleswade BESS31 May 202428 Sep 202957 MW
Biggleswade PV20 Dec 202431 Oct 203149.9 MW
Biggleswade31 May 202431 Oct 20341,000 MW
Biggleswade BESS31 May 202431 Oct 2034200 MW
Biggleswade High Impact Green Energy Hub20 Dec 202431 Oct 20341,000 MW
Greengage Farm27 Sep 202431 Oct 2034500 MW
Noventum - Biggleswade31 May 202431 Oct 2037249 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2029: 57 MW2031: 107 MW2034: 2.8 GW2037: 3.1 GW202920312033203520373.1 GW
0 MW2.0 GW4.0 GW2029: 57 MW2031: 107 MW2034: 2.8 GW2037: 3.1 GW20292032203520373.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202957 MW
2031106.9 MW
20342,806.9 MW
20373,055.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Biggleswade BESS57 MW0 MW28 Sep 20291gate 1Scoping
2Biggleswade PV49.9 MW57 MW31 Oct 20311gate 1Awaiting Consents
3Biggleswade1,000 MW106.9 MW31 Oct 20341gate 1Scoping
4Biggleswade BESS200 MW1,106.9 MW31 Oct 2034not statedgate not printedScoping
5Biggleswade High Impact Green Energy Hub1,000 MW1,306.9 MW31 Oct 2034not statedgate not printedScoping
6Greengage Farm500 MW2,306.9 MW31 Oct 20341gate 1Scoping
7Noventum - Biggleswade249 MW2,806.9 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2029157 MW
2031149.9 MW
203442,700 MW
20371249 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Biggleswade (Biggleswade 10 Renewables Limited)Hybrid1,000 MW31 Oct 2034Scoping
Biggleswade High Impact Green Energy HubHybrid1,000 MW31 Oct 2034Scoping
Greengage FarmHybrid500 MW31 Oct 2034Scoping
Noventum - BiggleswadeHybrid249 MW31 Oct 2037Scoping
Biggleswade BESSBattery storage200 MW31 Oct 2034Scoping
Biggleswade BESSBattery storage57 MW28 Sep 2029Scoping
Biggleswade PVHybrid49.9 MW31 Oct 2031Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.