Capacity1,200 MWBattery storage, Gate 1
Connection date28 Oct 2037Status as printed: Awaiting Consents
First date seen 30 Oct 2026, difference +4016 dayscalculated by N84
First date seen 30 Oct 2026, difference +4016 dayscalculated by N84
MW ahead in N84's order at this site57 MWcalculated by N84
Connection date, edition by edition
Only one edition so far
N84 holds one edition of this register for the project, so there is no earlier date to compare. The chart appears when a later edition is collected.
Observed changes
Showing changes in files dated from 23 Sep 2026.
- 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO TEC Register, file dated 20 Oct 2026, row 1243Receipt: NESO TEC Register, file dated 11 Sep 2026, row 1223
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.